Project Name / Site:  Black Pool Mill Retaining Wall Reconstruction

Sector: Historic Buildings

Scope of Work: Temporary Works Design, Cofferdam Design, Structural and Geotechnical Engineering

Project Overview

Amrose Associates was appointed to design a temporary cofferdam to support the reconstruction of a collapsed riverside retaining wall at the historic Black Pool Mill near Narberth, Pembrokeshire.

In October 2023, following heavy rainfall and high tides, a substantial section of the stone-faced retaining wall collapsed into the River Cleddau Ddu, just months after the Grade II*-listed mill reopened as a heritage restaurant following a multi-million-pound restoration.

The temporary cofferdam would create a dry working area within the river, allowing the retaining wall to be rebuilt safely.

The Challenge

The main challenge was designing a cofferdam that would provide a stable working area without unnecessarily restricting the river channel.

A wider structure would offer greater stability but could also reduce the space available for water to flow, potentially increasing the risk of upstream flooding.

Seasonal changes in river levels were another important factor, as higher water levels would increase the pressure acting on the structure.

The design needed to balance these considerations while providing sufficient space for the retaining wall construction works.

Our Approach

Amrose designed a cofferdam measuring 4.2 metres wide and 2.75 metres high, using two layers of AquaBag units:

  • Outer layer: Rock-filled bags to provide stability and reduce the force of flowing water.
  • Inner layer: Clay-filled bags to resist water pressure and minimise seepage into the working area.

The design was checked for sliding, overturning and the bearing resistance of the riverbed to ensure stability while keeping the structure as compact as possible.

Amrose also reviewed 12 months of river-level data from a monitoring station approximately 1 km upstream. This showed:

  • Summer: River levels generally below 1 metre.
  • From September: Significantly higher water levels.
  • Design limit: A maximum permissible water level of 1.5 metres for the planned early-summer works.

The team clearly communicated these limits to the client to help ensure construction was planned around safe river conditions.

The Outcome

Amrose delivered a compact, stable cofferdam design that would enable the retaining wall to be reconstructed within a dry working area while minimising obstruction to the River Cleddau Ddu.

By combining structural and geotechnical engineering with site-specific river-level data, the team developed a practical solution that addressed the challenges of working within a live river environment.

The project demonstrates Amrose Associates’ ability to develop temporary works designs that balance structural stability, environmental conditions and construction requirements.